Scheduled Road Reblockings/ Repair/ Improvement/ Equipment Installation in Metropolitan Manila

MANILA WATER Excavation for Sewer Lines Replacement Project from January 05- April 19, 2016
-Along West Avenue (Sidewalk Only) and North Lawin Alley, Brgy. Philam, Quezon City 

DPWH - MMIIDEO Road Repair and Reblocking from January 08- May 06, 2016
-Along A.P. Reyes Avenue towards Pasig River (Northbound) Brgy. Carmona, District I, Makati City
-Along South Super Highway from Homonhon St. towards Maribacan Creek, Brgy. Magallanes, District I, Makati City
-Along South Super Highway from SSH Box Culvert towards Zanzibar Creek, District I, Makati City 

DPWH - SMED Road Repair and Reblocking from January 08- June 07, 2016
-Along Pres. Quirino Ave. (Canonigo St.) Chainage 0 – Chainage 763 and Vicinity, Paco, Manila 

DPWH - QCSED Road Repair and Reblocking from January 08- May 06, 2016
-Along C.P. Garcia St. (Intermittent Section) Quezon City 

DPWH - QCSED Rehabilitation of Drainage System from January 08- July 05, 2016
-Along Katipunan Ave. (Broadcast City to B. Serrano Avenue, Intermittent Section) 3rd LD Quezon City 

DPWH - QCSED Rehabilitation of Drainage System from January 15- July 12, 2016
-Along Aurora Blvd. from EDSA to 15th Ave., (Intermittent Section) Quezon City 

DPWH - QCSED Rehabilitation of Drainage System from January 15- July 12, 2016
-Along Katipunan Ave. (B. Serrano to Broadcast City Intermittent Section) 3rd LD (Northbound) Quezon City 

DPWH - MMIIDEO Rehabilitation and Improvement of EDSA from January 08- June 05, 2016
-Magallanes Tunnel Drainage System and its vicinity, District I, Makati City 

DPWH - SMED National Road Lighting Program, Package 8 Civil Works, Completion of Roxas Blvd. East Service Road from January 20- July 17, 2016
-Along Cities of Manila and Pasay 

DPWH - LPMDEO Construction of Pedestrian Overpass from January 22- June 29, 2016
-Along DaangMaharlika (LZ) infront of SM Muntinlupa, Brgy. Tunasan, Muntinlupa City Sta. 

DPWH - SMED Rehabilitation/ Major Repair of Permanent Bridges EDSA Flyover (Southbound) from January 22- May 20, 2016
-Along Roxas Blvd. - EDSA Flyover, Pasay City 

DPWH - MMIIDEO Widening of C-5 Road from January 22- June 19, 2016
-C-5 Road, Makati City 

DPWH - QCSED Concreting/ Widening and Drainage Improvement/ Rehabilitation from January 22- December 23, 2016
-Along Mother Ignacia St. Quezon City 

Robinsons Communities Installation of Temporary Overhead Safety Canopy ang Temporary Use of One (1) Lane during Delivery of Materials for Robinsons Chimes Greenhills- Annapolis from January 29- March 13, 2016
-At No. 13 Annapolis St., Brgy. Greenhills, San Jauan City 

DPWH- MMIIDEO Improvement Cleaning and Declogging of Airport Road Outfall from January 30- June 27, 2016
-Along Brgy. Baclaran, Parañaque City 

DPWH- QCSED Rehabilitation of Drainage System (on sidewalk only) from February 1- May 30, 2016
-Along EDSA (NB) from Main Ave. to Aurora Blvd. (Intermittent Section), Quezon City 

DPWH- QCSED Rehabilitation of Drainage System (on sidewalk only) from February 1- July 9, 2016
-Along EDSA (NB) from Aurora Blvd., to Lagarian Creek beside Q- Mart Market, Quezon City 3rd LD 

DPWH- QCSED Rehabilitation of Drainage System (on sidewalk only) from February 1- July 29, 2016
-Along B. Serrano Ave. EDSA to Katipunan Ave., Quezon City 

MMDA TEC Construction of Pedestrian Steel Footbridge from February 3- July 1, 2016
-At Katipunan Ave. - Gate 1, Quezon City 

DPWH- MMIIDEO Road Repair for Drainage Improvement from February 5- July 3, 2016
-Along A. Arnaiz from Amorsolo St., to EDSA, Brgy. San Lorenzo, District I, Makati City 

DPWH- QCSED Rehabilitation of Drainage System (on sidewalk only) from February 26- June 24, 2016
-Along EDSA (NB) from White Plains to Gate 3 of Camp Aguinaldo Phase II, Quezon City, 3rd LD 

DPWH - NMED Road Repair/ Rehabilitation Improvement (Asphalt Overlay with Drainage Improvement) from February 5 to May 4, 2016
-Along Abad Santos St., Tondo Manila. 

C.M Pancho Const., Inc. Temporary Construction of Fence from February 5,2016 to May 4, 2016
-At No. 71 - A Scout Borromeo St., Brgy. South Triangle, Quezon City 

DPWH-LPMDEO Construction of Pedestrian Overpass from February 12,2016 to April 26, 2016
-Along CAA Road, Brgy. CAA, Las Piñas City 

DPWH-LPMDEO Construction of Pedestrian Overpass from February 12,2016 to April 26, 2016
-Along Alabang - Zaporte Road, Brgy. Pamplona, Las Piñas City 

DPWH- NCR Road Repair for National Road Lighting Program Package 9 (Civil Works) from February 19- October 15, 2016
-Along Caloocan C-3 Road from NavotasBdry. / C-3 Bridge to Kabanatuan St. 

DPWH - MMIIDEO Drainage System Improvement from February 17- June 15, 2016
-Along Chino Roces Avenue towards Pasig River, Makati City 

DPWH- QCFED Road Repair for Concrete Reblocking and Asphalt Overlay from February 19- May 8, 2016
-In Commonwealth Ave. South Bound. Quezon 

MDC Installation of Overhead Safety Protection- Canopy from February 19- May 19, 2016
-Along EDSA Ayala Ave., Makati City 

DPWH- SMED Road Repair Clearance for Retrofitting/ Strengthening of Permanent Bridge at Pedro Gil I Bridge from February 25- April 24, 2016
-At Pedro Gil St., City of Manila 

DPWH- QCFED Road Repair for Construction/ Rehabilitation of Maria Clara St., Quezon City from February 25- April 24, 2016 

PLDT Co. Excavation for Construction of Manholes and 4 x 63 mm Pipe thru HDD from February 19- June 18, 2016
-Along Sales Road and NAIA Road, Parañaque City
-Along Macapagal Blvd., Pasay City 

DPWH- SMED Excavation for Rehabilitation/ Reconstruction/ Retrofitting of Existing Permanent Bridge from February 19- June 18, 2016
-Along New Panaderos St., Sta. Ana, Manila 

DPWH- SMED Retrofitting/ Strengthening of Permanent Bridges from Februry 25- April 24, 2016
-At Pedro Gil Bridge along PengPedrio Gil St., City of Manila 

DPWH- NMED Road Repair Clearance for Drainage Improvement from February 25- July 23, 2016
-Along C-2 Road (Estero De Vitas to R- 10), Tondo Manila 

DPWH- QCFED Road Repair for Completion of Drainage Improvement from February 25- August 22, 2016
-Along EDSA South Bound, Brgy. BagoBantay, Quezon City 

DPWH- NMED Road Repair Clearance for MFO1 - National Road Network Services - Rehabilitation/ Reconstruction / Upgrading of Damaged Prave National Roads including Drainage Based on Pavement Management System / Highway Development and Management -4 (HDM- 4) from February 27 - May 16, 2016.
-Along G.Tuazon St., Manila, 4th LD 

DPWH- NMED Road Repair Clearance for Rehabilitation / Reconstruction / Upgrading of Damaged Paved National Roads including Drainage from February 27 t- May 26,2016.ent System / Highway Development and Management -4 (HDM-4) from February 27 - May 23,2016.
-Along J. Fajardo St., Sampaloc, Manila, 4th LD. 

DPWH- NMED Road Repair Clearance for Rehabilitation / Reconstruction / Upgrading of Damaged Paved National Roads including Drainage from February 27 o May 26,2016.
-Along P.Florentino St., Sampaloc, Manila, 4th LD 

DPWH- NMED Road Repair for Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved National Roads including Drainage Based on Pavement Management System/ Highway Development and Management from February 27- May 26, 2016
-Along Nagtahan Bridge Road, Sta. Mesa, Manila, 6th LD 

DPWH- NMED Road Repair for Construction of Flood Control Drainage from February 27- June 24, 2016
-Along Francisco Street, Crossing G- Tuazon and Loreto St., Sampaloc, Manila 

DPWH- NMED Road Repair for Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved National Roads including Drainage National Roads including drainage along Zaragosa St., Tondo, Manila from February 27- June 25, 2016 

DPWH- NMED Road Repair for Construction Maintenance of Flood Mitigation Structures and Drainage System from February 27- June 25, 2016
-Along Pureza St., crossing Lardizabal and Arevalo, Sampaloc, Manila 

DPWH – Road Repair Clearance for Construction / Upgrading / Rehabilitation of Drainage System from March 15 to June 27, 2016
-At Scout Ybardaloza street, Quezon City 

DPWH – Road Repair Clearance for Drainage Improvement from March 15 to October 10, 2016.
-At Mabini Street Pedro Gil Street and M.H. Del Pilar Street, Malate Manila. 

DPWH – Road Repair Clearance for Drainage Improvement from March 15 to June 23, 2016.
-Pedro Gil Street from Taft Avenue to Pedro Gil Bridge, Manila 

DPWH – Road Repair/ Rehabilitation / Reconstruction/ Upgrading of Damage Paved National Roads including Drainage based on Pavement Management System / Highway Development and Management from March 15 to June 12, 2016.
-At Claro M. Recto Avenue, District III, Quiapo, Manila City 

DPWH – Road Repair Clearance for MFO-2 Flood Management Services, Construction / Maintenance of Flood Mitigation Structures and Drainage System – Construction of Flood Control and Drainage Structures (RCBC) from March 15 to June 2, 2016.
-At Quezon Blvd. and Escalado Street, Manila City 

DPWH NMED- Road Repair for MFO- 2 Flood Management Services, Construction/ Maintenance of Flood Mitigation Structures and Drainage System- Construction of Flood Control and Drainage Structure (RCBC) from March 15- June 2, 2016
-Along Quezon Blvd. and Escalado St., Manila (Quezon Blvd. to Estero De Quiapo) 

DPWH- SMED Road Repair for Rehabilitation / Improvement of Drainage System from March 11- June 8, 2016
-Along Pres. Quirino from Taft Ave. to Leveriza St., City of Manila 

DPWH- SMED Road Repair for Rehabilitation / Improvement of Drainage System from March 11- June 8, 2016
-Along Pres. Quirino Ave. from Mabini St. Roxas Blvd., City of Manila 

DPWH- NMED Road Repair for Construction/ Rehabilitation of Various Infrastructure Projects from March 11, 2016 to June 8, 2016
-Pampanga St. (Juan Luna to Earnshaw St.) City of Manila, 2nd LD 

DPWH- SMED Road Repair Clearance for Drainage Improvement from March 15 to June 23, 2016
-Along Pedro Gil St. from taft Ave. to Pedro Gil Bridge #2 

DPWH- QCSED Road Repair for Rehabilitation / Improvement of Drainage System from March 15- June 27, 2016
-Along Scout Ybardaloza St., Quezon City 

DPWH- NMED Road Repair for Construction/ Rehabilitation of Various Infrastructure Projects from March 11, 2016 to July 8, 2016
-Molave St., (Bugallon to Solis St.) 

DPWH- SMED Road Repair for Drainage Improvement from March 15- October 10, 2016
-Along Mabini St. Pedro Gil St. and M.H. Del Pilar St., Malate, Manila 

DPWH-SMED Rehabilitation / Improvement of Drainage System from March 28-June 25,2015
-Along Pres. Quirino Avenue from Roxas Blvd., to Adriatico St., Manila 

DPWH-SMED Rehabilitation / Improvement of Drainage System from March 28-June 25,2015
-Along U.N. Avenue from Ma. Orosa St., to Taft Ave., Ermita, Manila 

DPWH-SMED Rehabilitation / Improvement of Drainage System from March 28-June 25,2015
-Along Pres. Quirino Avenue from Taft Avenue to Singalong, Malate, Manila 

DPWH-NCR Construction/ Upgrading/ Rehabilitation of Drainage from April 1,2016 to September 22, 2017
-Along National Roads, Katipunan St., Concepcion Dos, Marikina City 

GLOBE TELECOM Installation of FOC and Erection of Two (2) Globe Concrete Post from April 1 to April 16, 2016
-Along SM Annex North EDSA, Quezon City 

Integrated Contractor & Plumbing Works, Inc.- Construction of Drainage Manholes and Drainage Pipe Tapping to Existing Concrete Drainage Manholes from April 4, 2016 to June 12, 2016
-Along Sto. Cristo St. cor. Shaw Blvd., Mandaluyong City 

Manila Water Co., Inc.- Construction of North Pasig - Package 1, Main Sewer Interceptor Network from March 31, 2016 to January 19, 2018
-Along E. Rodriguez Avenue (C-5) Bagumbayan and Ugong Norte, Quezon City; Ugong (C-5) Doña Julia Vargas, BagongIlog and Pineda (Shaw Blvd.) Pasig City 

DPWH-SMED Rehabilitation / Reconstruction of Damage Paved National Road including Drainage Based on Pavement Management System / Highway Development Management-4 (HDM-4) from April 4, 2016 to September 30, 2016
-Along San Marcelino St. District V, Manila 

DPWH-SMED Rehabilitation / Improvement of Drainage System from April 8, 2016 to July 6, 2016
-Along Conception St. from P. Burgos St. to Ayala Blvd., ZobelRoxas St. Malate, Manila 

Manila Water Co., Inc. Installation of New Water Service Connection from April 9,2016 to April 25, 2016
-Along EDSA fronting Lux Center, Brgy.,Wack - Wack, Mandaluyong City 

DPWH- QCFED Construction of Pedestrian Overpass (Footbridge) from April 8, 2016 to September 4, 2016
-Along TandangSora Avenue, Old Balara, Quezon City 

DPWH-SMED Rehabilitation / Improvement of Drainage System from April 8,2016 to July 6, 2016
-Along T.M. Kalaw St. Roxas Blvd., to Ma. Orosa St. (SB) Ermita, Manila 

DPWH-LPMDEO Construction / Rehabilitation of Flood Control Structures Drainage System from April 8,2016 to September 4, 2016
-Along Alabang - Zapote Road, Almanza 1, Las Piñas City, Metro Manila 

DPWH-SMED Rehabilitation / Improvement of Drainage System from April 5,2016 to June 3, 2016
-Along A. Linao St. from P. Quirino Avenue to P. Gil St., Manila 

Makati Commercial State Ass. (MACEA) Construction of Ayala - Buendia Pedestrian Overpass from April 1, 2016 to March 31, 2017
-Along Sen. Gil Puyat Avenue fronting Makati Post Office, People's Support And Fronting RCBC Plaza, Makati City. 

MERALCO/R.E. Installation of Two (2) Poles and Meralco Facilities for Euro Towers Int'l., Inc. ( Vivaldi Residences - Bank 1) from April 9,2016 to April 23, 2016
-Along Edsa North Bound Murphy, Socorro, Cubao, Quezon City 

MMDA-TEC Soil Boring Test for Design and Construction of Pedestrian Footbridge from April 9,2016 to April 15, 2016
-Along R. Magsaysay Blvd., - Araneta Avenue, Quezon City 

C.M. Pancho Const., Inc. Temporary Use of One Lane for the Delivery of Construction Materials and Concrete Pouring from April 8,2016 to July 6, 2016
-At No. 71 - A Scout Borromeo St. Brgy., South Triangle, Quezon City 

DPWH-NMED MFO 1- Flood Management Services/ Maintenance of Flood Mitigation and Drainage Improvement from April 15, 2016 to September 21, 2016
-At Nepomuceno (Velasquez- Estero De Vitas), Manila City 

DPWH-QCFED Repair/ Rehabilitation of Road and Drainage from April 15, 2016 to December 10, 2016
-Along Banawe St., Quezon City 

DPWH-QCSED Improvement/Upgrading of Quezon Ave. from April 20, 2016 to September 16,2016
-Along BMA to Biak Na Bato Street (Both Direction) Quezon City 

DPWH-NMED Construction of Flood Mitigation Structures (RCBC) from April 20, 2016 to June 18, 2016
-Along Tolentino Street (S.H. Loyola to EspañaB Blvd.) Sampaloc, Manila 

BangkoSentralngPilipinas Construction of Drainage System from April 5,2016 to May 14, 2016
-Along BIR Road and East Avenue, Quezon City 

DPWH- NMED Construction of Flood Mitigation Structures (RCBC) from April 20, 2016 to July 30, 2016
-Along Gastambide St. (J. Dela Rosa to S.H. Loyola) and (S.H. Loyola St. (Gastambide to P. Noval St.) Sampaloc, Manila.